Todd & Cunningham Schools Roof Rehabilitation

Client: School District of Beloit

Location: Beloit, WI

Completed: 2013

Cost: $29,453.75 

FEI Services: Analysis

Contractor: McDermaid Roofing and Design Construction Administration Insulating Co.


FEI provided the review and analysis of existing conditions and documents in the Owner’s possession for Todd and Cunningham Elementary Schools, development of design solutions and construction documents, bidding support services, and construction administration services. 

Various roof areas required removal and proper disposal of select roofing system components, preparation of substrates for installation of new roofing systems, installation of new TPO roofing systems and insulation on specified areas, and installation of new and salvaged sheet metal components as specified.

Chimney rehabilitation was required at both Todd and Cunningham Elementary Schools,  consisting of down stacking and disposing of masonry materials for various chimneys, installation of new receivers and rebuilding of chimney, followed by installation of new concrete chimney crowns with drip and flashing, and finally  new stainless steel flue liners.