Client: Highland School District
Location: Highland, WI
Completed: 2013
Cost: $11,551.25
FEI Services: Investigation, Analysis & Design
Contractor: CGC, Inc.
FEI conducted analysis and assessment of existing (asphalt and concrete) pavements, curb and gutter, and related site drainage issues, with particular attention paid to the drive lane in front of the school. Inspection included observation, soil boring and SPT boring. FEI compiled findings into a formal report detailing the Project Scope, Executive Summary, Observations, and Recommendations.